Mitsubishi Heavy Industries, Ltd. (MHI) has been awarded a contract from Japan’s National Institutes for Quantum Science and Technology (QST) related to the ITER experimental fusion reactor(1),(2) currently under construction in southern France. The contract is for manufacture of 12 additional units of the Outer Vertical Target, a key component of the Divertor. MHI received this order in recognition of its accumulated technologies for mass production of components with a high degree of manufacturing difficulty, and follows the initial production order for manufacture of six units (Unit 1 – Unit 6) received in 2021.(3) With the additional 12 units (Unit 7 – Unit 18), MHI will handle manufacture for 18 of the total 54 units. Production of these units will be completed successively, with delivery to QST expected to begin in 2026.