Completion of Road/Bridge Work under Pradhan Mantri Gram Sadak Yojana

As per the programme guidelines of Pradhan Mantri Gram Sadak Yojana (PMGSY), the timeline for completion of road work is 12 working months from the date of issue of the work order. However, where a package comprises more than one road work, the total time given for completion of the package is 18 calendar months. Similarly, a time period of 21-24 months has been allowed for completion of bridge works exceeding 25-meter in length, depending on site conditions. The implementation of all sanctioned works under PMGSY is being monitored through online Monitoring Information System named ... Read more